Vang Danh- Đien Cong port- Quang Ninh province 1000mm track gauge Railway Improving, Upgrading

EMPLOYER:       DA BAC Storage Company- VINACOMIN

1. Work scope carried out by Construction Joint Stock Company No 6:

- Improve, upgrade railway.

- Excavate track bed, excavate channel, construct drainage channel.

- Replace rail, sleeper, turnout on railway

- Install new track 1000mm

2. Main work amount:

                              Track bed, drainage

            Excavate soil grade 3                           37.081  m3

            Fill soil track bed K95                           35.871  m3

            Construct ashlar channel                       1.908    m3

                  Superstructure              

            Remove rail P43                                    920       Units

            Remove concrete sleeper                       8.698    Units

            Remove turnout                                     16      Units

            Install prestressed concrete sleeperTN1  15.380  Units

            Install new track                                     9.750     M

            Add ballast                                            25.562  m3

3. Total Work Value:                 98.190.248.000 dongs

(In word: Ninety eight billions, one hundred ninety millions, two hundreds forty eight thousands dongs)

4. Construction Time:

- Start:                                                              8/2005

- Complete:                                                       2010