EMPLOYER: MỸ THUẬN PROJECT MANAGEMENT UNIT
1. Work Scope:
- Expand, improve road
2. Main Work Amount
- Excavate soil: 54.594 m3
- Fill soil: 11.279 m3
- Fill sandi: 145.828 m3
- Engineer fabric: 140.347 m2
- Drive sheeting pile: 16.719 (100m)
- Lay stone: 40.845 m3
- Drive sand pile D40: 21.476m
- Lay medium grain asphalt concrete: 88.057m2
- Lay fine grain asphalt concrete: 86.510 m2
- Produce and construct separator 0.85m high: 4.053 m
- Construct round culvert D1500: 197m
- Construct round culvert D1000: 24 m
- Construct frontage road, retain wall at bridge end: 580 m
- Supplement drainage system along road: 5.891 m
- Expand Dong Tâm intersection: 321,4 m2
3. Total Work Value: 98.190.248.000 dongs
(In word: Ninety eight billions, one hundred ninety millions, two hundreds forty eight thousands dongs)
4. Construction Time:
- Start: 8/2005
- Complete: 2010