EMPLOYER: RAILWAY PROJECT MANAGEMENT UNIT REGION I
1. Work scope:
- Construction in in-use track.
- Carry out abutment, pile, girder; bridge ends; railway underpass, road underpass.
2. Main work amount:
- Carry out abutment M1, bridge ends, load-reduction platform at Hà Nội direction of Tam Bạc bridge;
- Carry out abutment M2 + 50m load-reduction platform at Hải Phòng direction of Tam Bạc bridge.
3. Total contract value: 102.792.748.801 dongs
(In word: One hundred two billions, seven hundreds forty eight millions seven hundreds forty eight thousands eight hundreds one dongs)
4. Construction time
- Start: 2/2012
- Complete: 2013