1. Scope of work:
- Class: Class III, mountainous region
- Design velocity, Vtk = 60km/h
- B = 18.1m; Bmat= 15m
- Expand and renew foundation
- Hot asphalt concrete pavement
- Replace weak soil
- Cutting soil, mining for road bed
- Reinforced concrete ditch, pile culvert, reinforced concrete box culvert
2. Main work:
- Cutting soil for road bed: 74.782m3
- Filling soil: 105.286m3
- Replace weak soil: 14.642m3
- Macadam aggregate: 28.634m3
- Asphalt concrete pavement: 7.329m2
- Culvert: 17pieces/394.8md
- Reinforced concrete ditch: 6.061md
- Safety traffic system (iron sheet): 1.143md
- Sidewalk for pedestrian: 13.088m2
3. Total value: 38.048.584.741 vndong
( In word: Thirty eight billion, forty eight million, five hundred and eighty four thousand, seven hundred and forty one vndong)
4. Construction time:
- Commencement: 3/2001
- Complete: 6/2004