Construction: Alignment connecting from intersection Phuoc Lam pagoda- intersectionDong Tam Km1971+700, Highway 1A, under project: HoChiMinh city-Trung Luong highway (Stage 1)

1. Scope of work:

                        - Expand and renew road.

2. Main work

                        - Excavate soil:                                                             54.594m3

                        - Filling soil:                                                                  11.279m3

                        - Filling sand:                                                                145.828m3

                        - Install geotextile fabric:                                                            140.347m2

                        - Driving sheeting pile:                                                   16.719(100m)

                        - Laying stone aggregate:                                              40.845m3

                        - Driving sand pile D40:                                                 21.476m

                        - Medium-grained asphalt concrete:                                88.057m2

                        - Fine-grained asphalt concrete:                                     86.510m2

                        - Produce and execute median strip 0.85m:                    4.053m

                        - Pile culvert D1500:                                                      197m

                        - Pile culvert D1000:                                                      24m

                        - Frontage road, retaining wall of bridge:                                    580m

                        - Drainage system:                                                        5.891m

                        - Expand intersection Dong Tam:                                   321,4m2                                               

3. Total value:              98.190.248.000 vndong

(To word: ninety eight billion, one hundred and ninety million, two hundred and forty eight thousand vnd)

4. Construction time:

- Commencement:                                                                                             2005

- Complete:                                                                                                       2010