1. Scope of work:
- Install new track, mountainous region in Quang Ninh
2. Main work:
- Excavate subgrade: 3.863 m3
- Cutting soil for ditch: 140 m3
- Filling soil: 112.087m3
- Replace and install new wooden sleepersi: 1906 bars
- Supplement for installing timbers: 132 bars
- Supplement stone for track, turnout: 1350 m3
- Supplement for installing rails accessories: 212 sets
3. Contract value: 17.026.938.000vndong
(In word: seventeen billion, twenty six million, nine hundred and thirty eight thousand vndong only)
4. Construction time
- Commencement: 2008
- Complete: 2010