Railway at Lan Thap station, under project: Upgrading railway with gauge 1000mm Vang Danh-Dien Cong port- Quang Ninh province

1. Scope of work:

2. Main work:

- Filling soil K95:                                                                                                           18.660,73m3

- Cement mortar M100 thickness 2cm:                                                                            1.556,02m2

- Precast form:                                                                                                              1.873,30m2

- Install ditch pieces:                                                                                                      715 pieces

- Remove rails P43, L=12,5m:                                                                                        12 bars

- Remove concrete sleepers:                                                                                          133 bars

- Remove timbers:                                                                                                         56 bars

- Install wooden sleepers:                                                                                              34 bars

- Install sleepers K3A+accessories:                                                                                39 bars

- Levelling and tamping:                                                                                                 2.705 sleepers

- Adjust sleepers:                                                                                                          2.705m

- Ballast for making track shoulder:                                                                                 3.515m

- Adding ballast for track, turnout:                                                                                  1.403m3

- Ballast for new track, new turnout                                                                                 2.472m3

3. Contract value:                     21.995.396.000 vndong

(Twenty one billion, nine hundred and ninety five million, three hundred and ninety six thousand vnd only)

4. Construction time:

- Commencement:                                                                                                                     2010

- Complete:                                                                                                                    2011