1. Scope of work:
2. Main work:
- Filling soil K95: 18.660,73m3
- Cement mortar M100 thickness 2cm: 1.556,02m2
- Precast form: 1.873,30m2
- Install ditch pieces: 715 pieces
- Remove rails P43, L=12,5m: 12 bars
- Remove concrete sleepers: 133 bars
- Remove timbers: 56 bars
- Install wooden sleepers: 34 bars
- Install sleepers K3A+accessories: 39 bars
- Levelling and tamping: 2.705 sleepers
- Adjust sleepers: 2.705m
- Ballast for making track shoulder: 3.515m
- Adding ballast for track, turnout: 1.403m3
- Ballast for new track, new turnout 2.472m3
3. Contract value: 21.995.396.000 vndong
(Twenty one billion, nine hundred and ninety five million, three hundred and ninety six thousand vnd only)
4. Construction time:
- Commencement: 2010
- Complete: 2011