1. Scope of work:
- Subgrade, superstructure of track operation.
2. Main work:
*Subgrade:
- Cutting soil: 24.226,83m3
- Excavate for side ditch(C3): 7.034,87m3
- Heaving subgrade: 536,38m3
- Filling soil behind retaining wall, ditch: 2.689,22m3
- Revetment+ditch: 4.047m
* Superstructure:
- Screen-Undercut stone, replace wooden sleeper by PC sleepers at mixed gauge crossing :19,5km
- Overhaul turnout for sleepers, turnout accessories: 24 sets
- Remove old wooden sleepers: 770 bars
- Remove old wooden sleepers of mixed gauge crossing: 22.327 bars
- Remove old concrete sleepers of mixed guage crossing: 12.350bars
- Install new concrete sleepers: 29.747bars
- Ballast undervitting, cleaning for foundation: 24.570m
- Add ballast for turnout: 45.210m3
3. Contract value: 94.693.121.500 vndong
(Ninety four billion, six hundred and ninety three million, one hundred and twenty one thousand, five hundred vnd)
4. Construction time:
- Commencement: 2/2009
- Complete: 6/2010