Package No.5: Replace wooden sleepers by concrete sleepers at section Km101+000-Km120+500 and replace reused concrete sleepers for tracks at Chi Lang, Dong Mo  
Back Print Yahoo

1. Scope of work:

- Subgrade, superstructure of track operation.

2. Main work:

                        *Subgrade:

                        - Cutting soil:                                                                            24.226,83m3

                        - Excavate for side ditch(C3):                                                     7.034,87m3

                        - Heaving subgrade:                                                                  536,38m3

                        - Filling soil behind retaining wall, ditch:                                      2.689,22m3

                        - Revetment+ditch:                                                                    4.047m

                        * Superstructure:

                        -  Screen-Undercut stone, replace wooden sleeper by PC sleepers at mixed gauge crossing                                                                                                                                 :19,5km

                        - Overhaul turnout for sleepers, turnout accessories:                   24 sets

                        - Remove old wooden sleepers:                                                 770 bars

                        - Remove old wooden sleepers of mixed gauge crossing:                       22.327 bars

                        - Remove old concrete sleepers of mixed guage crossing:          12.350bars

                        - Install new concrete sleepers:                                                   29.747bars

                        - Ballast undervitting, cleaning for foundation:                            24.570m

                        - Add ballast for turnout:                                                                        45.210m3

3. Contract value:                     94.693.121.500 vndong

(Ninety four billion, six hundred and ninety three million, one hundred and twenty one thousand, five hundred vnd)

4. Construction time:

- Commencement:                                                                                 2/2009

- Complete:                                                                                           6/2010

Last updated: 07/10/2014