Construction: Consolidate railway at Hai Van Pass  
Back Print Yahoo

1. Scope of work:

                        - Consolidate railway

2. Main work:

                        - Cutting soil for making drainage ditch, filliing soil for slope:                   9.347m3

                        - Rubble stone for making slope:                                                                       2.440m3

3. Contract value:                     9.285.161.000 vndong

(In word: nine billion, two hundred and eighty five million, one hundred and sixty one thousand vndong only)

4. Construction time:

- Commencement:                                                                                 3/2009

- Complete:                                                                                           9/2009