Improve railway from Binh Dinh to Khanh Hoa following urgent order'  
Back Print Yahoo

1. Scope of work:

- Repair urgently on damaged track operation due to natural calamity

2. Main work:

- Item 14: Km1148+250-  Km1148+550: excavate soil, cutting soil for foundation class 3, Filling soil K95, buffer macadam, making track shoulder, adding ballast,...

- Item 26: Km1212+690 - Km1213+350: Excavate for track shoulder, the slope; cutting soil, filling foundation hole, ..

- Item 27: Km1213+350-Km1217+300: Construct railway bridge

- Item 32: Km1229+900 -Km1230+800: Install steel grid, cutting rock, filling rock, drain mouth, curb, revetment, culvert, reinforced concrete retaining wall,..

3. Contract value:                     78.561.100.000 vndong

(Seventy eight billion, five hundred and sixty one million, one hundred thousand vnd only)

4. Construction time:

- Commencement:                                                                                 2010

- Complete:                                                                                           2010