1. Scope of work:
- Upgrading railway
2. Main work:
| Subgrade | | |
| Cutting soil class 1 | 7856,21 | M3 |
| Cutting soil class 3 | 46284,5 | M3 |
| Cutting soil for foundation pit | 630,996 | M3 |
| Filling soil class K95 | 40969,7 | M3 |
| Turf | 5865,5 | M2 |
| Cutting soil for ditch class 3 | 879,01 | M3 |
| Rubble stone for making drainage ditch | 421,34 | M3 |
| Superstructure | | |
| Install railway inside station with rail P43m, PC sleepers TN1, track gauge 1m, R>400m | 2330,5 | m |
| Install railway inside station with rail P43m, PC sleepers TN1, track gauge 1m, R<400m | 59,6 | M |
| Install turnout, track gauge 1m rails P43 | 16 | bộ |
| Ballast for foundation | 2666,74 | M3 |
| Ballast undervitting, cleaning for turnout | 600 | M3 |
3. Contract value: 29.538.183.000 vndong
(Twenty nine billion, five hundred and thirty eight million, one hundred and eighty three thousand vnd only))
4. Construction time:
- Commencement: 2012
- Complete: 2012