EMPLOYER: DONG ANH District PROJECT MANAGEMENT UNIT
1. Work scope:
- Permanent bridge
- Load weight H30-XB80
- Width: B=0.5+11.0+0.5=12m
- Design procedure: procedure 22 TCN 18-79
- Đùng bridge: T prestressed reinforced concrete beam, L=33m, 5 units, reinforced bar pile 35x35cm
- Ống bridge: T prestressed reinforced concrete beam, L=15m, 06 units, reinforced bar pile 35x35cm
- Bài bridge: T prestressed reinforced concrete beam, L=15m, 06 units, reinforced bar pile 35x35cm
- Kè K4 bridge: girder cover plate L=7.2m, 12 units, reinforced bar pile 35x35cm
2. Main work amount:
- Drive reinforced bar pile 35x35cm: 4.192m
- Excavate soil: 3.000m3
- Fill soil: 17.000m3
- Ashlar: 666 m3
- Steel: 130 tons
3. Total contract value: 21.635.031.000 dongs
(In word: Twenty one billions, six hundreds thirty one millions, thirty one thousands dongs)
4. Construction time
- Start: 9/2008
- Complete: 5/2009