1. Scope of work:
- Install new track
2. Main work:
- Cutting soil for subgrade: 20.200m3
- Cutting rock class 3: 13.000m3
- Remove concrete sleeper: 3.827 bars
- Remove wooden sleepers: 326 bars
- Ballast for making track shoulder: 8.435m
- Supplement new rails: 40 bars
- Adjust sleepers: 6.073 sleepers
- Levellling and tamping: 6.073 sleepers
- Add ballast to old track: 2.585m3
- Remove rail P43: 503.bars
- Ballast for new track: 7.870m3
- Level crossing: 2 tracks
3. Contract value: 85.712.512.000 vndong
( Eighty five billion, seven hundred and twelve million, five hundred and twelve vnd only)
4. Construction Time:
- Commencement: 2009
- Complete: 2010