Package 17: Upgrade section Km909+516- Km919+152; Km949+383- Km958+270; Km991+604- Km1003+900 and make shop drawing project
EMPLOYER: RAILWAY PROJECT MANAGEMENT UNIT REGION 2
1. Work scope:
- Install new rack
2. Main work amount:
Track bed
a. Realignment
Excavate track bed 3.390,24 m3
Fill track bed 5.153,34 m3
Excavate stone 764,35 m3
b. Non-realignment
Excavate track bed 8.859,51 m3
Mark layer 2.045,1 m3
Fill track bed 5.758,35 m3
Carry out cutoff dike 1.948,86 m3
Excavate foundation 3.279,59 m3
Fill soil after construction 1.637,47 m3
Superstructure
Remove old concrete sleeper 31.036 units
Old steel sleeper 5.477 units
Old wood sleeper 914 units
Remove rail P43 L=12,5 4.202 units
rail 25 231 units
Carry out track bed stone 18.840,19 m
Add ballast into old track 27.726,62 m3
Install sleeper DWL+accessories 40.724 units
Install wood sleeper
Install steel sleeper 2.582 units
Install new track: 0.9 km
3. Total contract value: 190.354.344.000 dongs
(One hundred ninety billions, three hundreds fifty four millions three hundreds forty four thousands dongs)
4. Construction time:
- Start: 2010
- Complete: 2012