1. Scope of work:
- On track operating
- Auger-cast piles, temporary structure, abutment, steel girder, dismantle girder; superstructure, cutoff dike, quarter cone, track work approaches of bridges following approved shop drawing and meet technical requirement.
2. Main work:
- Auger cast piles D=10.2m: 560m
- Reinforce steel abutment f>=10: 0.16tons
- Reinforce steel abutment f<=18: 9.33 tons
- Reinforce steel abutment f>18: 3.25 tons
- Platform: 348.5m2
- Cutoff dike, quarter cone
- Auger cast piles D=1.2m: 560m
- Replace rail P43 L=12.5m on timber: 136 bars
- Replace guard rail P43 on timber L=12.5m: 13 bars
- Track shoulder: 182.4m
3. Contract value: 17.425.357.000 vndong
(In word: Seventeen billion, four hundred twenty five million, three hundred and fifty seven vietnam dong only)
4. Construction time
- Commencement: 5/2010
- Complete: 12/2010