Asphalt concrete pavement section Km499T-Km510T, under section Hien-Thach My, project: Ho Chi Minh highway section Km243+00-Km251+758.35  
Back Print Yahoo

1. Scope of work:

- Expand and renew road bed

- Execute hot asphalt concrete pavement

- Cutting soil, replace weak soil

- Cutting soil, mining stone of road bed

- Construction stabilization

            2. Main work:

- Excavate road bed      :                                                                                   162.638m3

- Filling soil:                                                                                                      179.785m3

- Replace weak soil                                                                                            18.353m3

- Macadam aggregate:                                                                                       419.340m3

- Asphalt concrete pavement:                                                                             186.389m2

- Reinforced concrete ditch                                                                                8404md

- Ditches:                                                                                                          24piecesi/804md

- Rubble stone for making revetment, reinforced concrete                                   7pieces/628md

- Safety traffic system (iron sheet)                                                                     3303md

3. Contract value:                     69.046.135.497 vndong

(In word: sixty nine billion, forty six million, one hundred and thirty five thousand, four hundred and ninety seven vndong)

4. Construction time:

- Commencement                                                                                              9/2000

- Completed                                                                                                      6/2004

Last updated: 07/10/2014