1. Scope of work:
- Expand and renew road bed
- Execute hot asphalt concrete pavement
- Cutting soil, replace weak soil
- Cutting soil, mining stone of road bed
- Construction stabilization
2. Main work:
- Excavate road bed : 162.638m3
- Filling soil: 179.785m3
- Replace weak soil 18.353m3
- Macadam aggregate: 419.340m3
- Asphalt concrete pavement: 186.389m2
- Reinforced concrete ditch 8404md
- Ditches: 24piecesi/804md
- Rubble stone for making revetment, reinforced concrete 7pieces/628md
- Safety traffic system (iron sheet) 3303md
3. Contract value: 69.046.135.497 vndong
(In word: sixty nine billion, forty six million, one hundred and thirty five thousand, four hundred and ninety seven vndong)
4. Construction time:
- Commencement 9/2000
- Completed 6/2004