1. Scope of work:
- On track operating.
- Permanent PC bridge;
- Design load: HL93;
- Parameter: Width 12m (including parapet); length: 197.85m, span structure using reinforced concrete girder I with L33m; H=1.65.
2. Main work:
- Cast, Drive pile 35x35cm; auger cast pile
3. Contract value: 52.706.000.000 vndong
(In word: fifty two billion, seven thousand and six million vietnam dong only)
4. Construction time
- Commencement: 2/2012
- Complete 4/2013