1. Scope of work:
- Construct railway on track operating.
- Screening- Undercutting stone + adding stone;
- Replace damaged sleepers by new concrete sleepers + elastic accessories;
- Excavate track bed;
- Replace rail P43/ concrete sleepers K3A spring spike
- Overhaul steel bridge floor
- Overhaul level crossing
2. Main work:
- Excavate track bed: 2.413m3
- Filling soil for track shoulder: 6.928m3
- Heaving track bed: 366m3
- Construct revetment: 1399m3
- Replace rails P30 by rails P43/concrete sleepers K3A accessories: 13.653m
- Replace rail P30 by rail P43/sleeper accessories: 650m
- Adding stone 4x6: 14.573m3
- Overhaul steel bridge floor: 33m
- Install guard rails on bridge: 384m
- Dismantling guard rails on bridge: 504m
- Level crossing: 6 pieces
3. Contract value: 29.440.266.000 vndong
(In word: twenty nine billion, four hundred and forty million, two hundred and sixty six thousand vnd only)
4. Construction time:
- Commencement: 1/2004
- Complete: 1/2005