Construction: Upgrading highway No.2 Km104-Km109, section Hung temple- Doan Hung  
Back Print Yahoo

1. Scope of work:

            - Upgrading highway

2. Main work:

            - Excavate:                                                       4.739m3

            - Excavate improper soil:                                   15.237m3

            - Excavate old pavement:                                  2.038m3

            - Filling soil K95:                                               45.292m3

            - Filling soil K98:                                               3.657m3

            - Filling sand K90:                                             4.512m3

            - Geotextile fabric:                                             10.279m2

            - Macadam aggregate type 1, type 2                              14.360m3

            - Coating impregnated bitumen:                         44.058kg

            - Macrograph grained asphalt concrete, fine grained       3.511m3

            - Reinforced PC girder:                                      10 pieces

3. Contract value:                     18.436.800.000 vndong

(In word: eighty billion, four hundred and thirty six million, eight hundred thousand vndong only)

4. Construction time:

- Commencement:                                             12/2007

- Complete:                                                       3/2008

Last updated: 07/10/2014