1. Scope of work:
- Expand and renew road.
2. Main work
- Excavate soil: 54.594m3
- Filling soil: 11.279m3
- Filling sand: 145.828m3
- Install geotextile fabric: 140.347m2
- Driving sheeting pile: 16.719(100m)
- Laying stone aggregate: 40.845m3
- Driving sand pile D40: 21.476m
- Medium-grained asphalt concrete: 88.057m2
- Fine-grained asphalt concrete: 86.510m2
- Produce and execute median strip 0.85m: 4.053m
- Pile culvert D1500: 197m
- Pile culvert D1000: 24m
- Frontage road, retaining wall of bridge: 580m
- Drainage system: 5.891m
- Expand intersection Dong Tam: 321,4m2
3. Total value: 98.190.248.000 vndong
(To word: ninety eight billion, one hundred and ninety million, two hundred and forty eight thousand vnd)
4. Construction time:
- Commencement: 2005
- Complete: 2010